CHEMICAL PLANT-PROCESS UNIT
For one of the main and reputed company in the field of polymer, our Engineering and Project Manager, and before creating MEC, he held the position of Project Manager and looked after the building a process unit. The scope of activities was the procurement, fabrication, erection, and commissioning of different equipment, structure and piping.
Supervision of fabrication and erection of pipe racks and structure: 43 T for a cost of around 50 thousand €
Supervision of fabrication and erection of 13 000 Inch Mtr of SS piping for a cost of around 100 thousand €
Supervision of procurement, fabrication, erection, and commissioning of SS tanks for a cost of around 140 thousand €